Wrangell, AK - Storage Tank Addition

Project included design and construction services for the addition of 435,000 K gallon bolted steel tank to improve reliability and meet high summer demands for existing water system serving City and Borough of Wrangell, AK.  Tank construction completed Fall 2010 at construction cost of $450,000.