Design and construction phase services for facilities to transport water from a new City well to the Mountain Springs transmission main. Design included a 200 horsepower line shaft turbine well pump with approximately 1,200 gpm capacity, chlorination via a sodium hypochlorite generator, a 20' x 20' building, and generator to provide emergency power for controls and chlorinator.
Larry Bellamy, City Administrator
City of Goldendale
(509) 773-3771
Goldendale, WA
Surveying, design and construction phase services for water system upgrades including metering 1500 services and replacing 15,000 feet of mains which reduced distribution system losses to less than 10%.
Planning, design and construction phase services including full-time inspection for a 1-mile intertie connecting two District water systems.
Design and construction services for new tank to improve reliability and meet high summer demands for an existing water system on Wrangell Island, Alaska.